MB Paratis provides construction technical supervision for onshore wind farms in Lithuania – from foundations and access roads to turbine installation, substations and grid connection. Since 2021 we have supervised the construction of more than 50 wind turbines with a total capacity of over 350 MW.
Our team has worked on wind energy projects since 2012, so we know the typical risks of each construction stage and help the investor keep quality, schedule and budget under control.

What we cover
- General technical supervision of construction works
- Special electrical supervision – MV and HV cabling, 110 kV substations and grid connection
- Supervision of access roads, crane pads and site infrastructure
- Supervision of land reclamation (drainage) works
- Construction health and safety coordination
- Construction management and on-site representation of the investor
How we work
- Review of design and contractor documentation before works start
- On-site quality control at every critical stage – foundations, reinforcement, concrete, installation
- Regular progress and schedule reporting to the investor
- Acceptance of works, as-built documentation and completion of construction



Selected wind projects
- Degaičiai wind farm, Telšiai district – 121 MW, 22 turbines, 2022–2025
- Potentia industriae wind farm, Jonava district – 71.5 MW, 13 turbines, 2021–2025
- Rokvėja wind farm, Rokiškis district – 66 MW, 12 turbines, 2021–2025
- Anykščių vėjas wind farm, Anykščiai district – 49.5 MW, 9 turbines, 2021–2025
- Vėjo miestas wind farm – 28 MW, 2023–2025
Planning a wind farm?
Tell us about your project – location, capacity and schedule – and we will prepare a technical supervision proposal.